Thursday, April 9, 2009

Project Scope Management PMP Sample Questions

Question No :1
Which is not part of project scope management?
(Choose correct one from multiple below)
1. Scope verification
2. Scope planning
3. Create WBS
4. None of the above
correct is :4
Explanations :
There are following processes which are part of Project Scope Management.
Scope Planning
Scope Definition
Create WBS
Scope Verification
Scope Control


Question No :2
If you are project manager for a Project and will need as many inputs to the initiation phase as possible. Of the following, which is the best source of information for your project?
1. Historical information
2. WBS
3. Business plans
4. None
correct is :1
Explanations : Historical information is the best input of the choices available.
B is incorrect since the WBS has not been created at this point of the project.
C is incorrect since business plans are not a likely input to the initiation process.


Question No :3
You are the project manager for the software Project.
This project must be completed within one year. This is an example of which of the following?
1. Schedule
2. Assumption
3. Constraint
4. Planning process
correct is :3
Explanations :
A project that must be completed by a deadline is dealing with time constraints.
A is incorrect since the condition does not offer a schedule.
B is incorrect because the condition is not an assumption.
D is also incorrect because this is not a planning process.


Question No :4
During the planning phase of your project, your project team members has discovered another
way to complete a portion of the project scope. This method is safer for the project team, but may
cost more for the customer. This is an example of _____ ?
1. Alternative identification.
2. Risk assessment.
3. Alternative selection.
4. Product analysis.
correct is :1
Explanations :
Alternative identification is a planning process to find alternatives to completing the project scope.


Question No :4
You are the project manager for a new Project. Your project is to create a new product for
marketing industry. You have recently knew that your competitor is also working on a similar
project but they are offering added web-based tools also, which your project does not offer.
You have implemented a change request to update your project. This is ___ .
1. A change due to an external event
2. A change due to an error and omission in the initiation phase
3. A change due to an error or omission in the planning phase
4. A change due to a legal issue
correct is :1
Explanations :
The change is requested to remain competitive with the competition an external event.


Question No :5
Which statement is not true about WBS ?
1. WBS serves as an input to activity sequencing.
2. WBS serves as an input to resource planning.
3. WBS serves as an input to activity definition.
4. WBS serves as an input to cost budgeting.
correct is :1
Explanations :
The WBS does not directly serve as an input to activity sequencing.
WBS serves as an input to resource planning, activity definition and activity definition.


Question No :6
If you are the project manager of a project and you changed the scope of a project to make the
final output less than the original baseline, you have _________ the project.
1. Rewritten
2. Truncated
3. Descoped
4. None
correct is :3
Explanations :
When you change the project plan by removing parts of the final deliverable, you have descoped the project.


Question No :7
Scope verification deals with the _______ from the customer?
1. Acceptance
2. Correctness
3. Quality
4. All of the above.
correct is :1
Explanations :
Scope verification deals with the Acceptance from the customer.


Question No :8
_________ is the word used in the PMBOK to define the breaking down of the WBS.
1. Decomposition
2. Scope definition
3. Scope verification
4. None
correct is :1
Explanations :
Decomposition is the word used in the PMBOK to define the breaking down of the WBS.


Question No :9
The project justification is a part of the ___________?
1. Scope Statement
2. Management plan
3. Project Plan
4. None
correct is :1
Explanations :
The project justification is a part of the Scope Statement.


Question No :10
Technical associations and consultants of project are two examples of __________ ?
1. Expensive additions
2. Scope managers
3. Expert judgment
4. External Resources
correct is :3
Explanations :
Expert judgment is most effective way of dealing with questions concerning choices of projects.
Expert Judgment: Expert judgment related to how equivalent projects have managed scope is
used in developing the project scope management plan.