Thursday, April 9, 2009

Project Procurement Management PMP Sample Questions

Question No :1
___________ is a groups of processes required to to purchase or acquire the products, services,
or results needed from outside the project team to perform the work.
(Choose correct one from multiple below)
1. Procurement Management
2. Planning Management
3. Scope Management
4. Control Management
correct is :1
Explanations :
Procurement Management is a groups of processes required to to purchase or acquire the
products, services, or results needed from outside the project team to perform the work.


Question No :2
The buyer and seller are bound by the ________.
(Choose correct one from multiple below)
1. contract
2. responsibilities
3. WBS
4. identification
correct is :1
Explanations :
The buyer and seller are bound by the contract.


Question No :3
PMI discusses procurement focusing on the ______ relationship .
(Choose correct one from multiple below)
1. buyer or seller
2. Vendor or seller
3. Purchasing
4. All of the above
correct is :1
Explanations :
PMI discusses procurement focusing on the buyer or seller relationship


Question No :4
In PMBOK, the seller is ________ to the project team.
(Choose correct one from multiple below)
1. Internal
2. External
3. Outside
4. Assigned
correct is :2
Explanations :
In PMBOK, the seller is External to the project team.


Question No :5 Delivery dates and availability of resources can be found in the details of the __________.
1. Work Breakdown Structure
2. SOW
3. Project Charter
4. Project Scope Statement
correct is :1
Explanations :
Delivery dates and availability of resources can be found in the details of the WBS.

No comments:

Post a Comment

ads

Kudos Good job dude ! Triumphs did it ! Share the joy with team ! Mood Your happiness meter!